• City of Tacoma QA
  • City of Tacoma Data




Rail Crossing Improvement

This Web Page is Available in 100+ Languages

Need this web page translated? 需要翻译此页面吗? ត្រូវការបកប្រែភាសាគេហទំព័រនេះមែនទេ? 이 웹페이지의 번역이 필요하십니까? Хотите перевести эту страницу? ¿Necesita traducir esta página web? Kailangan isalin ang pahina sa web na ito? Bạn cần dịch trang web này?

 

 

How to Translate this Web Page

This Web Page is Available in 100+ Languages

Need this web page translated? Please use the ‘Language’ button above to translate this page into one or more of 100 languages available. 需要翻译此页面吗?请使用上方的“语言”按钮,将此页面翻译成一种或多种语言,总计支持100种语言翻译。 ត្រូវការបកប្រែភាសាគេហទំព័រនេះមែនទេ? សូមប្រើប៊ូតុង 'ភាសា' ខាងលើដើម្បីបកប្រែភាសាទំព័រនេះជាភាសាមួយ ឬច្រើនជាង 100 ភាសាដែលអាចប្រើបាន។  이 웹페이지의 번역이 필요하십니까? 위의 ‘Language’ 버튼을 이용해 100여 개 언어 중 하나로 이 페이지를 번역할 수 있습니다.   Хотите перевести эту страницу? Воспользуйтесь кнопкой "Язык" выше, чтобы перевести эту страницу на один или несколько из 100 предложенных языков   ¿Necesita traducir esta página web? Utilice el botón “Idioma” de arriba para traducir esta página a uno o más de los 100 idiomas disponibles.   Kailangan isalin ang pahina sa web na ito? Mangyaring gamitin ang pindutan na ‘Wika’ sa itaas upang isalin ang pahinang ito sa isa o higit sa 100 wika na magagamit.   Bạn cần dịch trang web này? Vui lòng sử dụng nút ‘Ngôn ngữ’ ở trên để dịch trang này sang một hoặc nhiều thứ tiếng trong số 100 ngôn ngữ sẵn có

 

 

 

About the Project

The City of Tacoma has studied rail crossings in the Dome District, in Old Town, and in the West End.  Issues discussed/reviewed included safety, traffic operations, non-motorized mobility, noise, and economic or other quality of life issues.  These crossings have been identified as locations of concern by local residents, business associations, and property owners.  The rail lines at these locations are managed by BNSF, Sound Transit for commuter rail (AMTRAK and Sounder) and Tacoma Rail Mountain Division.

 

What Has Been Done and Next Steps

 

West End (6th Avenue and S. 19th Street) 

 

open house

Thank you for attending our virtual open house on February 17, 2021.  If you were unable to attend, click here to view a recording of the open house.  The ‘Question and Answer’ portion of the open house will be posted soon.  If you have any questions on the project, contact Project Manager Mark D'Andrea at mdandrea@cityoftacoma.org or (253) 591-5518.


Scope and Schedule: Pedestrian rail crossing improvements are planned at both the 6th Avenue and S. 19th Street rail crossings.  Select improvements include upgraded railroad signals, relocated vehicle railroad gates, the installation of new pedestrian railroad gates, sidewalks, curb ramps, pavement replacement, pavement markings/crosswalks, landscaping, signs and fencing.  Design, permitting and right-of-way activities are complete and the project has been advertised and awarded to a local contractor.  The City and BNSF will each be responsible for completing work in their respective rights-of-way (City to complete all sidewalks, paving, signage, etc.; BNSF will complete all rail gate/signal work).  

 

Project Updates

  •  4/28/22 – BNSF has started subsurface work at the S. 19th Street crossing, this will be followed by subsurface work at the 6th Avenue crossing.  Concrete crossing panels at both the S. 19th Street and the 6th Avenue crossings will be replaced next.  Once these are in place, the City’s Contractor will begin their work.  BNSF’s start date for the crossing panel replacement work is not yet known.  
  • 2/16/22 – Schedule Update: All documents between the City, the City’s Contractor and BNSF are now in place.  An onsite meeting was held the week of 11/1 to review the project and determine phasing.  BNSF is expected to begin work in March, the City’s Contractor will follow later in March/April depending on BNSF’s progress. 

Tentative Project Schedule for West End (6th Avenue and S. 19th Street)

  • October 2020: City advertises work at 6th Avenue and S. 19th Street for construction
  • April 2022: BNSF begins work onsite. BNSF's duration to be determined pending submittal of schedule.
  • June 2022: City's Contractor begins work onsite. Duration is expected to be approximately three months, pending weather delays.

McCarver Crossing
All crossing improvements have been installed. This includes new sidewalks, fencing, signs, pavement markings, upgraded rail signals, and the installation of two new pedestrian gates/signals on the east side of the crossing.
 
Dome District
In preparation for Quite Zone implementation, an onsite Diagnostic Meeting was held with representatives from Sound Transit, the Federal Railroad Administration and all other rail entities using the E. C Street and E. D Street crossings.  Draft layouts have been assembled for each crossing, and contracting, design and construction discussions have been ongoing with Sound Transit.  Further work at these two crossings is on hold due to COVID-19 related budget impacts.
  

Final Rail Crossing Report

The final report addressing these rail crossings were completed in October 2018. 

Rail Crossing Evaluation Report, October 2018 Rail Crossing Evaluation Report Appendices

  

Rail Crossings Map

This map shows the general location of the crossings analyzed.  

Map

West End (6th Avenue and S. 19th Street)

Project Funding

 

Funding Source
Amount
City of Tacoma     $70,000
Federal Highway Safety and Improvement Grant        $1,106,750
 State Funds     $1,150,000

 

Dome District (E. C and E. D St. Crossings)

As of June 2020, this project is currently on hold.

 

Contact Information

If you have questions or comments you can contact City of Tacoma Project Manager, Mark D'Andrea, at (253) 591-5518 or by email.