Join Tacoma Tree Foundation for a discussion about trees in Tacoma. These meetings are an opportunity to share your preferences about which trees should be planted in your neighborhood. Information gathered at these meetings will be shared with the City of Tacoma to help inform decisions made about trees in the Madison District, South Tacoma area and other city-led projects. It will also help inform choices made about which trees to offer for the Grit City Trees Program and in upcoming Tacoma Tree Foundation plant giveaways. For more information and ways to participate visit treesfortacoma.org.
Project Overview
The Madison District Green Infrastructure project is intended to improve neighborhood streets, fix drainage problems, and protect Puget Sound from polluted runoff by installing permeable pavement. Permeable pavement allows rainwater falling on streets to soak into the ground and eventually, to the groundwater.
The Environmental Services Department received a grant from the Washington State Department of Ecology and has partnered with the Public Works Department and Tacoma Water to replace the streets and utilities in the Madison District, shown in blue on the map below.

With support from these partnerships, the project is planning to replace and/or install the following:
- Permeable pavement (also known as pervious asphalt)
- Non-permeable pavement (also known as standard asphalt)
- Continuous sidewalks
- Walking and biking path
- Additional street trees picked by property owners
- Street drainage
- Sewer pipes
- Drinking water pipes
The typical roadway and sidewalk once completed will look similar to the graphic below. Streets may look slightly different then what is shown.

Walking and Biking Path
A new 10-foot wide walking and biking path is part of a larger plan to increase walkability by eventually building a looped path called the Loop Road. The planned Loop Road is shown in the below map. The Loop Road is planned to be installed on South 45th from Pine to Lawrence Street.

Why permeable pavement?
Replacing 16 residential streets (in need of improvement) with pervious pavement will improve the driving surface and help with water quality by infiltrating rainwater from the road surface. Currently, rainwater that is collected on the road surface in this neighborhood flows into catch basins, is piped to Flett Creek, Chambers Creek, and ultimately to Puget Sound. When this untreated rainwater (also known as stormwater) is piped to these bodies of water, it carries harmful pollutants from cars and human activities and discharges these pollutants into our water. This has a negative effect on plants, animals, humans, and entire ecosystem.
The permeable pavement installed as part of this project will infiltrate 28 acres of stormwater, rather than collecting it in a piped system. This infiltration process will allow pollutants to be filtered out by the soils, and allow clean stormwater to combine with the groundwater, which will help recharge the South Tacoma Aquifer. The South Tacoma Aquifer is used by the city as a supplemental source of drinking water.
View the Madison District Project Schematic Plan
View the Project Block-by-Block Plan
Funding
WA State Department of Ecology |
$6,600,000 |
Tacoma Water |
$1,000,000 |
Wastewater Utility |
$850,000 |
Project Schedule
Design |
June 2020 - June 2021 |
First Virtual Design Public Meeting |
February 18, 2021 at 12:00 p.m. |
Second Virtual Design Public Meeting |
Late Spring 2021 |
Advertise and Award Contract |
June - September 2021 |
First Virtual Construction Public Meeting |
End of Summer 2021 |