The week of October 12, 2015, weather dependent, the contractor expects to complete the 2015 striping project.
Remaining work includes:
- S. 96th St between A Street and Barnes Lane - Bike lane symbols, arrows, remaining stop bars, and raised pavement markers will be installed.
- South 15th at Tacoma Avenue South - Plastic Arrows and letters will be installed.
- South 9th and A Street - Plastic Arrows and letters will be installed.
- North 30th Street and Pearl - Plastic Arrows and letters will be installed.
- South 19th at Rosemount - Plastic Crosswalk will be installed.
- South 15th Street at Pacific Avenue - Plastic fog line will be installed.
- South 11th between Pacific Avenue and Tacoma Avenue South - Turn Arrows will be installed.