• City of Tacoma QA
  • City of Tacoma Data




 

Puyallup River Bridge

Puyallup River Bridge Aerial View

Puyallup River Bridge Project Updates-Bridge Closure Scheduled May 21, 2018 - February 2019

The City of Tacoma would like to inform you of the upcoming closure of the Puyallup River Bridge scheduled to begin Monday, May 21, 2018. The closure is anticipated to last nine months.

 

During the closure vehicles will be directed to the Lincoln Avenue Bridge and I-5 to cross the Puyallup River. See attached Detour Plans.

 

Phase I of the project began in March 2018 with the pole line to the south of the bridge being undergrounded.  This work did not affect traffic on the bridge.

 

Phase II of the project includes the actual demolition and replacement of three spans of the bridge west of the Puyallup River to the intersection of Portland Avenue and Puyallup Avenue. This is planned for May 2018 pending final agreements from both Union Pacific and BNSF railroads and final certification of the projects right of way needs.  The project anticipates being complete in February 2019.

  

Puyallup River Bridge Rendering

 

About the Bridge

The Puyallup River Bridge, that links Tacoma to the city of Fife to its east, was opened in 1927. It was opened as one of Washington's last segments of the famous Pacific Highway, also known as State Route 1 and in later years, Highway 99. The bridge is made up of seven steel-truss spans linked by reinforced concrete sections. It was financed in approximately equal measure by the federal and state governments, took barely more than a year to build, and was finished early and within budget. The bridge lost much of its daily traffic load when the first Washington segment of Interstate 5 opened in Tacoma in December 1960, but it has remained an important commercial arterial, linking Fife to Tacoma's industrial area and the facilities of the Port of Tacoma. In 2013, after more than 85 years of nearly trouble-free service, age and the elements were catching up with the Puyallup Avenue Bridge, and the City of Tacoma was well along with plans to replace 950 feet of the span on the Tacoma side of the river with a cable stay bridge.

 

Funding for this work was primarily split between two Federal grants, Bridge Replacement Advisory Committee (BRAC) and Surface Transportation Program (STP), to replace two sections of the bridge F16A and F16B along with a partial replacement of section F22.  No work is anticipated on the three sections spanning the river and running east. Augmenting the Federal funding were two State grants from the State Department of Commerce and the Freight Mobility Strategic Investment Board to replace these bridge sections.

Specifically the project will replace the bridge sections required to span the BNSF and Union Pacific Main Lines through Tacoma.  The project will have a right of way component and design review by both railroads and the State.  The Puyallup River Bridge is on an arterial street consisting of four travel lanes with three currently crossing over the bridge. Construction of the bridge will impact traffic patterns in the area forcing traffic onto I-5 and Lincoln Avenue Bridge.


Unfortunately the design work for a cable stay bridge proved financially unviable in 2013 and required rethinking of the project in order to protect the federal grants acquired to replace the bridge.  In February 2016 an Alternative Assessment Workshop was completed with WSDOT and other agencies and professionals to determine if the project should move forward.  The Workshop determined that the project was of value to the area and the bridge should be replaced.  Following the workshop, the design-build procurement process was found to be the only way to secure the Federal funding prior to the December 2016 obligation deadline.

 

The design-build selection process started in November 2016 when the City opened the RFQ and scored the ten statements of qualification received. Then in January 2017 the City issued the RFP to the three finalists selected. The design-build teams submitted their preliminary designs for scoring in April 2017.  The submittals received represented three different steel and concrete girder bridge designs.  On April 18, 2017 the City opened the proposals received.  Atkinson Construction was found to be the best value proposer with a design of a continuous span precast concrete girder bridge replacing F16 A&B and all of the F22 span.

 

All permits for the project have been updated. The Federal environmental documents have been approved.  The  project has received permission to phase its Right of Way acquisition to allow utility relocation work to begin prior to the anticipated demolition of the bridge.

Funding 

Source 

 Amount
 Bridge Replacement Advisory Committee - BRAC  $15,628,538
 Federal Funding - FHWA (STP)  $12,200,000
 Freight Mobility Strategic Investment Board  $5,000,000
 Dept. of Commerce  $6,950,000
 Port of Tacoma  $500,000
 City of Tacoma  $1,607,505

 

Schedule

 

Phase Estimated Start Date Estimated End Date
RFQ for DB Teams September 2016 November 2016
RFP for DB Teams November 2016 June 2017
Design/Construction June 2017 December 2018
Estimated Construction April 2018 February 2019
Anticipated Opening February 2019  

 

Questions and Comments

The City of Tacoma is managing the project. Contact City Project Manager Chris Storey with questions or concerns at (253) 573-2484 or via email.