• City of Tacoma QA
  • City of Tacoma Data




East 40th Street GSI and Utility Improvements

Overview

The City of Tacoma's Environmental Services Department, Public Works Department, and Tacoma Public Utilities have partnered to plan and implement an integrated approach to retrofit the East 40th Street roadway from McKinley Avenue to Portland Avenue. The new permeable roadway will be designed with traffic safety improvements for reducing speeds and an enhanced pedestrian and bicycle experience on a new shared use path. The improvements will also include green infrastructure bioswales, new stormwater and water pipes, and new sidewalks and curb ramps. Public and private utilities will also be replaced in coordination within East 40th Street from McKinley Avenue to Portland Avenue.

 

Upcoming Public Meeting

Meet the design team and find out more information on the planning details and project schedule at an upcoming public meeting on Wednesday, February 8, 2017 at 6 PM.

Meeting location:

        Blix Elementary School

        1302 East 38th Street, Tacoma, WA  98404

 

East 40th Street Improvements

View the Schematic Plan for the East 40th Street improvement project.

 

Improvements by Block

View the Block by Block Plans for the East 40th Street improvement project.

 

Funding

 

Source

Amount

Department of Ecology Grant

$1,850,250

Environmental Services Surface Water

$ 616,750

Tacoma Water

TBD

Public Works

TBD

Total

TBD

 

Schedule

 

Task

Estimated Start Date

Estimated End Date

Design

May 2016

April 2017

1st Public Design Meeting

October 11, 2016

 

2nd Public Design Meeting

February 8, 2017

 

Advertise and Award

April 2017

June 2017

Public Construction Meeting

June 2017

 

 

Questions