Rail Crossing Improvement: 6th Avenue and South 19th Street

How to Translate this Web Page

This Web Page is Available in 100+ Languages

Need this web page translated? Please use the ‘Language’ button above to translate this page into one or more of 100 languages available. 需要翻译此页面吗?请使用上方的“语言”按钮,将此页面翻译成一种或多种语言,总计支持100种语言翻译。 ត្រូវការបកប្រែភាសាគេហទំព័រនេះមែនទេ? សូមប្រើប៊ូតុង 'ភាសា' ខាងលើដើម្បីបកប្រែភាសាទំព័រនេះជាភាសាមួយ ឬច្រើនជាង 100 ភាសាដែលអាចប្រើបាន។  이 웹페이지의 번역이 필요하십니까? 위의 ‘Language’ 버튼을 이용해 100여 개 언어 중 하나로 이 페이지를 번역할 수 있습니다.   Хотите перевести эту страницу? Воспользуйтесь кнопкой "Язык" выше, чтобы перевести эту страницу на один или несколько из 100 предложенных языков   ¿Necesita traducir esta página web? Utilice el botón “Idioma” de arriba para traducir esta página a uno o más de los 100 idiomas disponibles.   Kailangan isalin ang pahina sa web na ito? Mangyaring gamitin ang pindutan na ‘Wika’ sa itaas upang isalin ang pahinang ito sa isa o higit sa 100 wika na magagamit.   Bạn cần dịch trang web này? Vui lòng sử dụng nút ‘Ngôn ngữ’ ở trên để dịch trang này sang một hoặc nhiều thứ tiếng trong số 100 ngôn ngữ sẵn có

 

 

This Web Page is Available in 100+ Languages

Need this web page translated? 需要翻译此页面吗? ត្រូវការបកប្រែភាសាគេហទំព័រនេះមែនទេ? 이 웹페이지의 번역이 필요하십니까? Хотите перевести эту страницу? ¿Necesita traducir esta página web? Kailangan isalin ang pahina sa web na ito? Bạn cần dịch trang web này?

 

About the Project

Pedestrian rail crossing improvements are planned at both the 6th Avenue and S. 19th Street rail crossings. Select improvements include upgraded railroad signals, relocated vehicle railroad gates, the installation of new pedestrian railroad gates, sidewalks, curb ramps, pavement replacement, pavement markings/crosswalks, landscaping, signage and fencing.  

The City and BNSF will each be responsible for completing work in their respective rights-of-way (City to complete all sidewalks, paving, signage, etc.; BNSF will complete all rail gate/signal work).  

 

Traffic Alert as of March 2023

Starting in March 2023, please watch out for the electronic signs onsite. Flaggers will be on site during the day. 


Provisions will be made for emergency services vehicles to cross the tracks. If businesses/residents need to make vehicle trips during this time, they are encouraged to find legal public parking on the east side of the tracks in advance of the crossing closure since the rail crew will facilitate/assist on-foot (or wheelchair) access across the tracks with worker escort. 

 

Proposed Project Schedule for West End (6th Avenue and S. 19th Street)

 

schedule map

 

The New Proposed Construction Schedule is as Follows:
  • March 6, 2023 – BNSF work starts on S.19th St. Crossing
  • March 13, 2023 – BNSF work starts on 6th Ave Crossing
Proposed Road Closures – Phase 1 BNSF

 

S. 19th Street Crossing

  • Will be completely closed in both directions from 8 PM - 7 AM, Monday, March 6 through Thursday, March 9, 2023 (Needs a minimum of 11 hours)
  • During the day, one (1) lane will stay open between 7 AM – 8 PM
  • The crossing will reopen for all traffic around 7 AM on March 10, 2023
6th Avenue Crossing 
  • Will be completely closed in both directions from 8 PM - 7 AM, Monday, March 13, 2023, through Thursday, March 16, 2023 (Needs a minimum of 11 hours)
  • During the day, one (1) lane will stay open between 7 AM – 8 PM
  • The crossing will reopen for all traffic around 7 AM on March 17, 2023

 

Project Updates

  • Spring/ Summer 2023: City's Contractor anticipated to begin work on site. Duration is expected to be approximately three months, pending weather delays.
  • First Quarter 2023: City to re-advertise work at 6th Avenue and S. 19th Street for construction. March 2023 – BNSF construction anticipated to begin. BNSF is scheduled to begin rail construction work in March 2023. Related City construction work will follow completion of BNSF work at each crossing.
  • January 2023- Design, permitting and right-of-way activities are complete. 9/8/2022- The City Contractor’s contract was terminated due to the delays. The project will be re-advertised.
  • June 20, 2022 - BNSF was scheduled to start the work at S. 19th and then proceed to 6th. Work was cancelled as the city received numerous concerns from the residents and businesses in the impacted area related to BNSF’s required 4-day, daytime closure at each crossing.


Public Outreach

A virtual open house was held on February 17, 2021.  If you were unable to attend, click here to view a recording of the open houseIf you have any questions on the project, contact the Project Manager, Veronicah Munyao at vmunyao@cityoftacoma.org or (253) 325-1152

 

West End (6th Avenue and S. 19th Street)

Project Funding Sources
Amount
City of Tacoma      $1,070,000
Federal Highway Safety and Improvement Grant        $1,304,314
 State Funds     $1,150,000

 

Contact Information

If you have questions or comments you can contact City of Tacoma Project Manager, Veronicah Munyao, at (253) 325-1152 or by email.

 



]]>