About the Project
The City of Tacoma has studied rail crossings in the Dome District, in Old Town, and in the West End. Issues discussed/reviewed included safety, traffic operations, non-motorized mobility, noise, and economic or other quality of life issues. These crossings have been identified as locations of concern by local residents, business associations, and property owners. The rail lines at these locations are managed by BNSF, Sound Transit for commuter rail (AMTRAK and Sounder) and Tacoma Rail Mountain Division.
What Has Been Done and Next Steps
West End (6th Avenue and S. 19th Street)

Thank you for attending our virtual open house on February 17, 2021. If you were unable to attend, click here to view a recording of the open house. The ‘Question and Answer’ portion of the open house will be posted soon. If you have any questions on the project, contact Project Manager, Veronicah Munyao at vmunyao@cityoftacoma.org or (253) 325-1152.
Scope and Schedule: Pedestrian rail crossing improvements are planned at both the 6th Avenue and S. 19th Street rail crossings. Select improvements include upgraded railroad signals, relocated vehicle railroad gates, the installation of new pedestrian railroad gates, sidewalks, curb ramps, pavement replacement, pavement markings/crosswalks, landscaping, signs and fencing. Design, permitting and right-of-way activities are complete, and the project has been advertised and awarded to a local contractor. The City and BNSF will each be responsible for completing work in their respective rights-of-way (City to complete all sidewalks, paving, signage, etc.; BNSF will complete all rail gate/signal work).
Project Updates
- January 2023 – Construction anticipated to begin. Currently, Public Works is coordinating with BNSF to schedule a new start date for the BNSF crossing work in early 2023. Related City construction work will follow completion of BNSF work at each crossing.
- 9/8/2022- The City Contractor’s contract was terminated due to the delays. The project will be re-advertised.
- 6/20/2022 - BNSF was scheduled to start the work at S19th and then proceed to 6th. Work was cancelled as the city received numerous concerns from the residents and businesses in the impacted area related to BNSF’s required 4-day, daytime closure at each crossing.
Tentative Project Schedule for West End (6th Avenue and S. 19th Street)
- January 2023: BNSF work at each crossing expected to begin. Crossing closure schedule will be coordinated with businesses and residents.
- First Quarter 2023: City to re- advertise work at 6th Avenue and S. 19th Street for construction.
- April 2023: City's Contractor anticipated to begin work on site. Duration is expected to be approximately three months, pending weather delays.
McCarver Crossing
All crossing improvements have been installed. This includes new sidewalks, fencing, signs, pavement markings, upgraded rail signals, and the installation of two new pedestrian gates/signals on the east side of the crossing.
Dome District
In preparation for Quite Zone implementation, an onsite Diagnostic Meeting was held with representatives from Sound Transit, the Federal Railroad Administration and all other rail entities using the E. C Street and E. D Street crossings. Draft layouts have been assembled for each crossing, and contracting, design and construction discussions have been ongoing with Sound Transit. Further work at these two crossings is on hold due to COVID-19 related budget impacts.
Final Rail Crossing Report
The final report addressing these rail crossings were completed in October 2018.
Rail Crossing Evaluation Report, October 2018
Rail Crossing Evaluation Report Appendices
Rail Crossings Map
This map shows the general location of the crossings analyzed.

West End (6th Avenue and S. 19th Street)
Project Funding
City of Tacoma |
$70,000 |
Federal Highway Safety and Improvement Grant |
$1,146,346 |
State Funds |
$1,150,000 |
Dome District (E. C and E. D St. Crossings)
As of June 2020, this project is currently on hold.
Contact Information
If you have questions or comments you can contact City of Tacoma Project Manager, Veronicah Munyao, at (253) 325-1152 or by email.