S. 56th to S. 58th Street East Side:
Sidewalk and driveway work has been completed.
S. 56th to S. 58th Street West Side:
The demolition, grading of sidewalks, forming of ADA ramps and driveways should be completed by January 13, 2016.
S. 58th to S. 66th Street West Side:
Completed.
S. 58th St. to S. 66th Street East Side:
Completed.
Grinding and overlay:
Work will begin Jan. 11, 2016 and is expected to be completed Jan. 15, 2016, weather dependent. Work hours will be from 7:30 pm to 6:00 am.
View the Project Map: