South Tacoma Way Update - January 7

South Tacoma Way Update - January 7

S. 56th to S. 58th Street East Side:

Sidewalk and driveway work has been completed.

S. 56th to S. 58th Street West Side:

The demolition, grading of sidewalks, forming of ADA ramps and driveways should be completed by January 13, 2016.

S. 58th to S. 66th Street West Side:

Completed.

S. 58th St. to S. 66th Street East Side:

Completed.

Grinding and overlay:

Work will begin Jan. 11, 2016 and is expected to be completed Jan. 15, 2016, weather dependent.  Work hours will be from 7:30 pm to 6:00 am.

View the Project Map:

STW - Update 1-7-16



]]>