Striping Contract 2015

Plastic markings will be placed, weather permitting, September 16 through October 5, 2015.  Work will occur Monday through Saturday.

 

The Contractor is starting on McKinley Avenue between 72nd and 96th, then plans to continue on Norpoint Way between 49th Avenue NE and 29th Street NE, and then S 96th from the West City Limits (Near Steele Street) to McKinley.

 

On Friday October 2, 2015 striping is planned for I-705 Schuster to S 12th, S 11th Pacific to Tacoma Avenue, Pacific at S 15th, S 15th Street at Tacoma Avenue, S 15th Street at St. Paul, S 19th At Rosemount, N 30th at Pearl and S 9th at A Street.



]]>