Pacific Avenue at SR 7 Safety Improvements

Project Description

Improve the visibility of traffic signal heads and improve the phasing, timing, and coordination between signals. Upgrade to accessible countdown pedestrian signals and push buttons, improve crosswalks, and upgrade signs.

 

Project Funding Update:

Source Amount
Federal Highway $945,166
City of Tacoma $50,000

Budget 

Phase Amount
Design $165,340
Right-of-Way $150,000
Construction $661,360

 Total

$976,700

 

Schedule 

The project is delayed due to partnership negotiation with WSDOT to add more curb ramps at more intersections along SR 7.

 

Phase               

Start Date       

End Date           

Advertising for Bids February 2018 April 2018
Construction July 2018 December 2018

 

Additional Information

For additional information contact the City's Project Manager, Said Seddiki, 

SSeddiki@ci.tacoma.wa.us or at (253) 591-5204