Project Description

Improve the visibility of traffic signal heads and improve the phasing, timing, and coordination between signals. Upgrade to accessible countdown pedestrian signals and push buttons, improve crosswalks, and upgrade signs.

 

Project Funding Update:

Source Amount
Federal High Way $945,166
City of Tacoma $50,000

Budget 

Phase Amount
Design $165,340
Right-of-Way $150,000
Construction $661,360

 Total

$976,700

 

Schedule 

Phase               

Start Date       

End Date           

Advertising for Bids November 2017 December 2017
Construction March 2018 September 2018 

 

Additional Information

For additional information contact the City's Project Manager, Said Seddiki, 